Timetable for Everest Expedition, North Col. |
Phase |
Description of Work |
Start and End Dates |
Phase One |
Preparation of expedition (personal fitness and material) |
October 1, 2014 – April 1, 2015 |
Phase Two |
Trip to Kathmandu, Nepal |
April 2, 2015 – April 3, 2015 |
Phase Three |
Start of expedition from Kathmandu to Based Camp and Advanced Base Camp (ABC), 6,500m/21,300ft |
April 12, 2015 – April 23, 2015 |
Phase Three |
Climbing period of Everest, 8,848m/29,029ft |
April 24, 2015 – May 26, 2015 |
Phase Five |
Trip from Advanced Base Camp to ‘Base Camp and back to Kathmandu |
May 27, 2015 – May 30, 2015 |
|
|
Time table for Vinson Expedition, Antarctica |
Phase |
Description of Work |
Start and End Dates |
Phase One |
Preparation of expedition (personal fitness and material) |
August 1, 2011 – November 10, 2011 |
Phase Two |
Trip to Punta Arenas, Chile |
November 11, 2011 – November 12, 2011 |
Phase Three |
Start of expedition from Punta Arenas to Patriot Hills, Antarctica |
November 13, 2011 – November 14, 2011 |
Phase Three |
Climbing period of Vinson, 4,897m / 16,067 ft |
November 15, 2011 – December 3, 2011 |
Phase Five |
Trip from Patriot Hills back to Punta Arenas |
December 4, 2011 |
|
|
|
|
 |
|
|
|